Proposed Sandy Point Wind Farm

With the proposed Sandy Point Wind Energy Project by the companies Community Wind and ABO Wind, our residents and the public are seeking information and answers. The Municipality of the District of Shelburne has compiled the below links to help provide that information, to help address questions. The first section references documents that pertain to Council and the Municipality; the second useful information for residents, public, agencies and organizations and another section of where residents and the public can go to seek answers to their questions. Updates to this page will be made when there are additional resources and new information to be added.

Update from ABO Wind:

ABO Wind and Community Wind have recently received word that the Sandy Point Wind Project was not selected for the shortlist of the Nova Scotia Rate Based Procurement. Feedback from the government regarding the Sandy Point Wind Project submission is expected in the coming months. At this time, ABO Wind and Community Wind have paused the project but will continue to evaluate this and other development opportunities in the region while we await the feedback. If you have questions about the project, please contact David Berrade of ABO Wind at  or by phone at 902-802-4540. 

Council Information:

Integrated Community Sustainability Plan (2010):

In 2010, the Municipality of the District of Shelburne adopted an Integrated Community Sustainability Plan (ICSP) after conducting comprehensive public engagement with its residents, resulting in a vision and goals for the Municipality for the next 20 years, including the following guiding principle pertaining to renewable energy:

“Our residents recognize the potential renewable energy has to enhance our local economy, and to benefit from this opportunity we need to make sure we identify and encourage development of renewable energy projects and create a facilitative policy environment for these projects.”

Integrated Community Sustainability Plan (ICSP)

ICSP Action Plan 

Council Announcements:

In response to a presentation to Council on September 22, 2021, by a community group, the Council felt that a status update regarding the Proposed Sandy Point Windfarm was necessary to emphasize the Council's long standing position on windfarm development, the anticipated future timeline of key events and the best way our citizens can direct questions going forward.

Council Update - 2021-09-24

Council Update - 2021-10-21

Council Reference Documents:

Letter of Support - 2021-07-07

Staff Report - 2015-09-28

Council Meeting Minutes - 2015-09-28

Council Meeting Minutes - 2015-10-26

Nova Scotia Power (1st Stage in approval process):

The premier of Nova Scotia has announced an aggressive, new renewable electricity standard, requiring 80 per cent of Nova Scotia’s electricity to come from renewable resources by 2030. As such the Province has launched the Rate Base Procurement process which aims to attract low-cost and innovative solutions to procure 350 MW of electricity for the province of Nova Scotia. This call for proposals will help the province get closer to the 80 per cent target and support the province’s goal of achieving a 53 per cent reduction in greenhouse gas emissions by 2030 and net-zero by 2050. The Procurement Administrator will conduct a request for proposal (RFP) process to identify the most competitive low-impact renewable energy projects. These projects will be awarded Power Purchase Agreements (PPAs) with Nova Scotia Power Inc. (NSPI) to supply renewable electricity generation for their customers. It is anticipated that Community Wind and ABO Wind will submit their proposal some time in November or December 2021.

Nova Scotia Rate Based Procurement

Nova Scotia Power Renewable Energy Targets

Environmental Assessment (2nd Stage in approval process):

Assuming Community Wind and ABO Wind are successful in being awarded a Power Purchase Agreement by Nova Scotia Power (the first key timeline event - anticipated in the Spring of 2022), Community Wind and ABO Wind would then have to complete an Environment Assessment (EA) that is anticipated to take another year to complete (The second key timeline event - anticipated in the Spring or summer of 2023). The EA process is the forum within which community members can ask questions and provide feedback for consideration by the Minster of Environment. As a matter of background, in 1989, environmental assessment was developed as an environmental management tool to allow for the consideration of public concerns relating to broad environmental issues when evaluating proposed developments. Environmental assessment ensures that environmental, human health, socio-economic, cultural, historical, architectural, and archaeological concerns from all stakeholders and the Mi’kmaq of Nova Scotia are identified and addressed at the earliest stage of development planning. Through consideration of these broad environmental issues and public and Mi’kmaq concerns, the Minister of Environment decides whether the development can proceed in an environmentally sustainable manner. Should the Minister approve the Proposed Sandy Point Windfarm EA then Community Wind and ABO Wind would then submit a planning application to the Municipality as per our By-Law L101 (the third and final key timeline event).

A Citizen's Guide to Environmental Assessment

Environmental Assessment Frequently Asked Questions

By-Law L101 (3rd Stage in approval process):

Assuming Community Wind and ABO Wind have their environmental assessment approved by the Minister of Environment, they would then have to submit a planning application to the Municipality as per our By-law L101. In accordance with the guiding principle of the ICSP, on October 26th, 2015, Council implemented one of the recommended actions which was to update and approve its Municipal Planning Strategy and Land Use By-law (L101). This action was to provide the municipal framework by which renewable energy developers would have to adhere. The By-law provides planning guidelines for various sizes of developments, including utility projects greater than 2 megawatts. It was these primary factors in which Council made the decision to provide a letter of support for the proposed windfarm project in Sandy Point. It is worth noting that Council passed the ByLaw based in part on the Staff Report dated September 28, 2015, that states specifically that "The purpose of the policy on wind turbine development is to generally encourage the development of wind turbines at all scales, with protections in place to minimize negative impacts on citizens and landowners." Following the first reading of the By-law on September 28, 2015, and a Public meeting on October 26, 2015, the Council concluded the second and final reading and unanimously passed the By-law.

By-Law L101

Useful Information:

Wind Turbine Effects

What does a wind turbine sound like? - Sound survey at Studland Windfarm, Tasmania

Where to direct your questions:

Community Wind and ABO Wind

There are two forums to which citizens can direct their questions and concerns in regard to the Proposed Sandy Point Windfarm project. The first is to direct your questions directly to Community Wind and ABO Wind who have created a new website that provides relevant information on the project and a method for submitting questions to the company. Please note that the Municipality have requested that Community Wind and ABO Wind post the questions they have received and the answers they subsequently provide to our citizens on their website (This includes questions and answers from the public meeting held on September 16th, 2021 at Sandy Point Community Hall). A representative from Community Wind and ABO Wind has assured the Municipality that they will comply with this request.

Community Wind and ABO Wind Website

Department of Energy & Mines 

In response to a request by citizen's for the Municipality to provide an independent third party expert to direct questions, the Municipality has arranged to provide a second forum for citizens questions. In this regard the Department of Mines & Energy have provided an email address for citizens to send their questions regarding windfarms, a webpage with frequently asked questions (soon to be posted) and a web link to an online form to ask questions regarding the environmental assessment process.

Department of Energy & Mines - Frequently asked questions

Department of Energy & Mines - Email address ()

Department of Energy & Mines (Environmental Assessment Question Form)

Municipality of Shelburne

The Municipality is happy to answer any questions as they pertain to the Municipality's Integrated Community Sustainability Plan and subsequent Bylaw L101. However, if you have specific technical questions pertaining to the Proposed Sandy Point Windfarm Project we ask that you direct them to either Community Wind and ABO Wind themselves or the Department of Energy & Mines. Any questions directed to the Municipality can be sent to CAO Trudy Payne at 

Community Questions

Please click the link below to review the questions and answers provided, in response to a list of questions submitted to the Municipality from the Stop Sandy Point Wind Committee. The Municipality will continue to answer questions from the community as they pertain to the Integrated Community Sustainability Plan and our By-law L101.

For those members of the community who have questions about the project itself, we ask that you contact the developer directly via their website. They have a question form you can complete as well as providing an email address and company contact. Their webpage address is https://www.abo-wind.com/en/the-company/international/canada/sandy-point-wind/. If you wish to ask procedural questions or wish to get answers from an independent third party, then we recommend you contact the Department of energy & Mines at .

2021-10-29 Stop Sandy Point Wind Committee Questions & Municipality Answers